Industrial · 2024

Riverside Logistics Hub

A 42,000 m² distribution warehouse with a reinforced slab rated for heavy racking, delivered from bare ground to operational in fourteen months.

The interior of a large steel-framed industrial hall, its floor cleared and roof structure exposed.Industrial
Site overview
  • Aerial view of a reinforced slab being laid, with a line of site staff walking the finished section.
    Slab pour
  • A steel portal frame picked out against a dark sky, its bracing forming a lattice.
    Portal frame
  • The interior of a completed distribution warehouse with pallet racking running the length of the floor.
    Racking install

Overview

The site was a former aggregate yard with two metres of uncontrolled fill across most of its footprint. We stripped, tested and re-engineered the ground before a single foundation was set, which added three weeks at the front of the programme and removed a settlement risk that would have followed the building for decades.

The warehouse slab was the critical element: laser-screeded, power-floated and cured to a flatness tolerance the client's racking supplier could sign off without remedial grinding. Dock levellers, sprinkler tanks and the office block ran as parallel packages so the building was weathertight before the first winter.

Scope of works

  • Ground remediation and re-engineered fill
  • Pad foundations and laser-screeded warehouse slab
  • Portal frame erection and cladding envelope
  • Two-storey office fit-out and external works

Project Spec

Location
Riverside District
Client
[Client Name]
Value
[Contract Value]
Duration
14 months
Floor area
42,000 m²